DENR ADMINISTRATIVE ORDER NO. 18-97

SUBJECT    :     Supplementing Guidelines for Environmental Impact Assessment of Forestry Project

     In line with the effort to strengthen the implementation of the Environmental Impact Assessment System for forestry projects, the following guidelines are hereby issued:

     SECTION 1.   Scope

     All forestry projects, unless covered by Article II, Section 2 of DAO No. 96-37, shall undergo an Environmental Impact Assessment.

     SECTION 2.   Preparation of EIS

     In preparing the Environmental Impact Statement for forestry projects, the proponent may refer to the Handbook on Environmental Impact Assessment for Forestry Projects and other relevant materials provided that, at all times, the proponent shall comply with DAO No. 96-37.  cdasia

     SECTION 3.   Coordination between the EMB and FMB

     The Environmental Management Bureau (EMB) shall coordinate with the Forest Management Bureau (FMB) in conducting the EIA for forestry projects.

     SECTION 4.   Transitory Provision

     All applications for 1997 IAOPs that have undergone Complete Staff Work (CSW) and final action by FMB as of April 30, 1997 and all application for IAOPs submitted in 1996 shall be processed in accordance with Section 3.7 of DMC No. 96-04.

     There is no final action by FMB if the IAOP is returned to the bureau for further action.

     This Administrative Order shall take effect immediately.   LLpr

(SGD.) VICTOR O. RAMOS

Secretary

 



CONTACT INFORMATION

Department of Agrarian Reform
Elliptical Road, Diliman
Quezon City, Philippines
Tel. No.: (632) 928-7031 to 39

Copyright Information

All material contained in this site is copyrighted by the Department of Agrarian Reform unless otherwise specified. For the purposes of this demo, information are intended to show a representative example of a live site. All images and materials are the copyright of their respective owners.